Special Notice to Cherry Hill Village Residents
Beginning Tuesday, October 11, we will be seal coating all asphalt roads and alleys in The Village. Although we are trying hard to minimize any inconvenience, in order to seal the roads, there may be a few days where access is limited. Street parking will likely be limited and you may have to park on another street for an overnight period.
We have requested that the asphalt company complete this project as quickly as possible with minimal interruption, however some inconvenience will be necessary in order to properly seal the roads. We need to perform this maintenance to save the roads from water and salt damage and help to reduce major road repairs.
The map (below and attached) will give you an idea of when to expect the asphalting to begin on your street. Please be mindful of safety and parking during this period. We expect to have good weather but that is the one unpredictable factor that could extend the project. You will be kept informed of any changes. K&J Asphalting will be doing this work and has already been here filling in cracks and repairing holes. In addition to this notification, KS Management has placed a schedule in everyone’s door or mailbox and the asphalt company will also be marking scheduled streets the night before with cones and barricades.
We regret any brief inconvenience this may cause, but again, it is necessary that we maintain the roads to reduce future costs.
Should you have any questions, please use the email address for KS Management listed on the attachment mike@ksmanagement.org
Thanks for your patience and continued support!
The Cherry Hill Board of Directors
Download CHV MASTER SEAL COATING LETTER 2011 (PDF)
The following areas are scheduled for seal coating, please park on adjacent streets
on your affected day. Notice of next day seal coating will be posted the night prior to in your area with orange cones/barrels & removed by contractors once that area is open for traffic, there will be a 24 hr. closure of sealed roadways. The Association could have a few areas that trash collection may not get picked up during this 8 day project.
Day 1: Scheduled date 10-11-2011 TUESDAY
- Area 1 – Jackson Ln. from Denton to Buchanan
- Area 3 – Harding St.
- Area 4 – Colonial
- Area 5 – Monroe between Roosevelt & Constitution
- Area 6 – Burr St.
But only 4 percent of viagra pills from india them would like to continue their use of the cream. This respitecaresa.org viagra on line purchase might simply cause devastating financial issues. Some examples of latest technology used for the treatment order cheap viagra of erectile dysfunction. 1. Kamagra Tablet is available at reasonable prices and adds pleasure to your love life. sildenafil shop
Day 2: Scheduled date 10-12-2011 WEDNESDAY
- Area 1- Taylor Ln.
- Area 2- Roosevelt St. from Jackson Ln. to Hancock St.
- Area 3 – Alleyway between Patriot & Roosevelt/First alleyway South. Of Harding & alleyway between Bldgs.
- G&H.
- Area 4- All alleyways
- Area 5 – All alleyways
- Area 6- All alleyways
Day 3: Scheduled date 10-13-2011 THURSDAY
- Area 1 – Garfield Ln. from Jackson Ln. to Buchanan.
- Area 2 – McKinley Circle
- Area 3 – Roosevelt from Harding to Hancock.
- Area 4 – Constitution from Independence to Monroe St.
- Area 5 – Filmore St. from Roosevelt to Monroe.
Day 4: Scheduled date 10-14-2011 FRIDAY
- Area 1 – Buchanan from Jackson to Garfield Ln.
- Area 2 – All alleyways
- Area 3 – All remaining alleyways
- Area 4 – All common parking
- Area 5 – Fillmore St from Monroe to Hancock
- Area 6 – Coolidge
Day 5: Scheduled date 10-15-2011 SATURDAY
- Area 2 – Buchanan St from Hancock to Jackson
- Area 3 – Roosevelt from Cherry Hill to Harding & Fillmore from Roosevelt to Hancock.
Day 6: Scheduled date 10-16-2011 SUNDAY
- Area 2 – Jackson Ln. between Buchanan & Roosevelt
- Area 3 – Patriot
- Area 4 – Hamilton
- Area 6 – Monroe St & Jefferson from Coolidge to Constitution
Day 7: Scheduled date 10-17-2011 MONDAY
- Area 2 – Hancock from Buchanan to Roosevelt
- Area 4 – Hancock from Liberty to Patriot
- Area 5 – Hancock from Patriot to Roosevelt
- Area 6 – Constitution from Grant to Jefferson
Day 8: Scheduled date -18-2011 TUESDAY
- Area 5 – Jackson Ln from Constitution to Roosevelt/Jefferson St. from Constitution to Roosevelt/Roosevelt from Jackson Ln. to Grant
Rain delays: Schedule will move forward as weather dictates.
IMPORTANT: ALL SPRINKLER SYSTEMS MUST BE TURNED OFF TO AVOID DAMAGE TO THE SEAL COATING